Mikron

Mikron's Arapahoe County facility was a tight schedule success story. Working closely with the developer and design team, Alcorn expedited entitlement and design resulting in approvals being received in only 3 months. Construction started in January, and although 20 of the first 40 working days were lost to weather, the project was delivered in the alloted 9 month timeframe. Design assistance was provided on the elaborate electrical bus rail system and cost option analysis facilitated an upgrade of the lighting to LED.

LOCATION

8100 S. Potomac St.
Englewood, CO 80112

DESCRIPTION

New 67,200 square foot, 24′ clear tilt-up concrete building wtih joist and deck structure on 4.96 acre site located in Arapahoe County, Colorado. We worked with Open Studio Architects, Venture Architecture, and Confluent Development.

DEVELOPER

Confluent Development

ARCHITECTURE FIRM

Open Studio Architecture